South African Roads Agency investigating non-payment of its contractors
The South African National Roads Agency (SANRAL) is investigating allegations of non-payment of subcontractors, unfair deductions, unfair treatment, and lack of training.
This comes after SANRAL received complaints from subcontractors about non-payment while working on the R390 road construction project between Cradock and Hofmeyr in the Eastern Cape.
However, the Roads Agency clarified that it only has contractual agreements with main contractors on its projects, but added that it sympathises with the subcontractors’ plight.
SANRAL added that it takes a dim view of reports of main contractors’ late payments to subcontractors, particularly when it culminates in disruptions to its projects.
“We recognise the role and responsibility that we play in helping to develop SMMEs that work on our projects, particularly the need to use our procurement initiatives to advance transformation in the construction industry,” said Kayakazi Mafuta, SANRAL’s Provincial Head for the Eastern Cape Province.
“Since the sub-contractors’ complaints surfaced in early October this year, SANRAL appointed an independent consultant to perform an in-depth audit of the said contract.”
In line with SANRAL’s mandate, the contractor ring-fenced 41 Targeted Work Packages (TWPs) for local qualifying small enterprises, with included skills and training programmes.
According to Mafuta, the agency received the initial audit outcomes and is awaiting the final report, which is due this month.
“Once the final report is received, SANRAL will then be in a better position to make an informed decision based on the outcomes of the audit,” she said.
Regarding the delayed payments, the preliminary investigation has revealed that none of the appointed Small, Medium, and Micro Enterprises (SMMEs) have been paid late to date.
As per the contract between SANRAL and the main contractor, the contractor is obligated to pay all SMMEs within 14 days of providing services.
Mafuta noted that the preliminary report does not cover other allegations that were made by the subcontractors, including unfair deductions, unfair treatment, and lack of training.
A critical part of SANRAL’s Eastern Cape investment

The project forms part of SANRAL’s broader R1.2 billion Eastern Cape regional road investment programme, alongside upgrades and maintenance on routes connecting Cradock, Tarkastad, Middelburg, Molteno, and Fish River.
According to the tender documents, the maintenance on the 62.50km stretch between Cradock and Hofmeyr involves structural pavement rehabilitation, drainage overhauls, and road safety upgrades.
These upgrades include surface rehabilitation and new pavement, strengthening roadbed layerworks and resurfacing seals to restore structural integrity and skid resistance.
Drainage and stormwater infrastructure is also being upgraded, including clearing waterways, constructing open drains, and replacing or upgrading prefabricated box and pipe culverts to prevent water damage.
Road safety and corridor furnishing upgrades include the installation of new guardrails along high-risk sections and replacement of roadside fencing to keep livestock off the national route.
It also includes active traffic accommodation, like Stop-and-Go controls, throughout construction zones for the duration of the project.
To ensure that the work meets quality assurance and environmental compliance, the contract included the construction of a dedicated on-site materials testing laboratory.
It also included independent construction-phase environmental monitoring, which complicated matters and added to the construction time.
Project mobilisation began in March 2023 under a 36-month baseline schedule, with ancillary tenders for site laboratory testing, environmental monitoring, and sanitation extending through 2024–2026.